During a tense May 21 Eureka City Council meeting, council members lamented that what they deemed a flawed process used to select finalists for a $370,000 annual marketing contract had broken the publicโ€™s trust.

Things have since gone from bad to worse amid new revelations, including that staff has repeatedly and materially misrepresented key facts about how the process played out.

The Journal has learned the council will meet in closed session to discuss one case of โ€œsignificant exposure to litigationโ€ stemming from the process that led to city staff recommending the council award the marketing contract to Humboldt Made, which already runs the Eureka Visitors Center, over a nationally acclaimed Virginia firm, Eddy Alexander. On May 21, the council opted to hold off on awarding the contract and to instead conduct another round of interviews with the two finalists, this time with marketing experts and a couple council members on the interview panel.

But the Journal has found that staff repeatedly provided inaccurate information to the public โ€” and the council at the May 21 meeting โ€” about problems with Humboldt Madeโ€™s initial proposal submittal and that of another firm that didnโ€™t make the final cut. The problems were in fact so substantial that City Manager Greg Sparks says that, knowing what he knows now, Humboldt Madeโ€™s proposal should have been rejected and not considered, quickly adding that he doesnโ€™t want to get out in front of City Attorney Bob Black, who is expected to brief the council on the findings an internal review of the matter and the legal ramifications on Tuesday.

At the heart of the matter is the question of whether Humboldt Made submitted its proposal complete and on time and, if not, whether that โ€œirregularityโ€ is something that should be considered non-material โ€” the kind of thing that can be waived while maintaining a fair process โ€” or substantive enough that it gave Humboldt Made a competitive advantage.

The cityโ€™s request for proposals asked interested firms to submit both a digital copy and 10 paper copies of their proposal by the close of business April 5 and warned โ€œany proposals received by the city after the hour and date shall be rejected and returned unopened.โ€ The RFP document also includes a disclaimer that the city โ€œfurther reserves the right at any time and for any reason to โ€ฆ alter this RFP if the conditions so dictate.โ€

The first hint that anything unusual might have occurred with Humboldt Madeโ€™s proposal came in a May 14 story by the Lost Coast Outpost, which reported on a string of text messages between Eureka Community Development Services Director Rob Holmlund and Humboldt Made Executive Director Alanna Powell that the website had obtained through a California Public Records Request. (The texts actually came as a part of three requests submitted to the city by two anonymous email addresses that requested a host of documents, including the texts associated with Powell and Holmlund. Itโ€™s unclear how the website learned of the requests.)

As first reported by the Outpost, on Sunday, April 7 โ€” two days after the cityโ€™s deadline for marketing proposals โ€” Powell texted Holmlund to say that the firm’s โ€œfinal version of the proposal was unfortunately not the copy that was sent to the printer.โ€ It seems that due to a staff error, the firm had inadvertently printed a rough draft and submitted it to the city. Holmlund asks if Humboldt Made submitted the correct digital version and Powell told him she was having a staff member check. The exchange is brief but Holmlund does not indicate the submittal error might be disqualifying.

When asked about this exchange by the Outpost, Holmlund, Sparks and Powell all reportedly said Humboldt Made had submitted the correct draft electronically by deadline so they deemed the application complete despite the error and the city allowed Humboldt Made to resubmit paper copies on Monday, April 8.

Councilmember Kim Bergel questioned Holmlund about this during the May 21 meeting.

โ€œWhen the proposals were submitted, I was working on a Sunday on the zoning code and got a text from the director of the visitorโ€™s center,โ€ Holmlund said. โ€œIt said one of my staff submitted the wrong copy of the proposal. I asked (Development Services Deputy Director Lane Millar) to look into it and there was a duplicate page so said just resubmit. And so I think Lane talked to the city manager as well. So they resubmitted, and so did another firm โ€ฆ .โ€

Councilmember Kim Bergel questioning city staff.

Bergel then asked if it was just the duplicate page that changed between the two print submittals or if any of the other content changed. Holmlund then deferred to Millar, saying he โ€œhandled this processโ€ and was thus better suited to answering the question.

โ€œIt was simply replacing the page with what should have been there,โ€ Millar said.

โ€œThere were no changes in any of the details โ€ฆ as far as changing words or anything like that?โ€ Bergel asked.

โ€œThe page in question did have content,โ€ Millar answered, again implying that the only issue was the duplicate page, which took the place of a page that should have been there.

In an interview with the Journal days after the council meeting, Holmlund repeated this characterization, saying that he never saw the original version but Millar told him the issue was limited to the duplicate page and that Humboldt Made had submitted its correct digital proposal by the April 5 deadline. Holmlund said the other firm referenced during the council meeting โ€” which the Journal has since learned was Vessel Strategy, a New York firm โ€” didnโ€™t have an error but just missed the deadline entirely.

Holmlund stressed in the interview that he felt the most important thing was getting the best possible proposals to make sure the cityโ€™s $370,000 in annual marketing money was well spent. He also pointed to the cityโ€™s procurement policy, which allows the cityโ€™s โ€œpurchasing agent, at his or her sole discretion,โ€ to โ€œwave inconsequential irregularities in bids received.โ€

Around the same time, Sparks told the Journal essentially the same thing, saying it was his understanding that the issue with Humboldt Madeโ€™s proposal was limited to the single page and that the correct electronic version had been submitted on time. He said he deemed it to be a โ€œminor correctionโ€ and also stressed that he felt it important to bring the best possible proposals to council.

On May 25, the Journal reached out to City Attorney Bob Black to get his impression of the seemingly contradictory clauses in the RFP and the city procurement policy and whether he deemed this all to be inconsequential.

โ€œI havenโ€™t been asked this question and I would need to take a look at the specific language in the RFP,โ€ Black said. He provided the Journal an update later in the day, saying โ€œthis question requires digging deeperโ€ and he would be in touch.

On Friday, Black told the Journal there are a number of issues at play. First, he said, the cityโ€™s procurement policy does allow for the โ€œpurchasing agentโ€ to issue waivers in limited circumstances. However, in this case, because the city is considering a contract of more than $100,000, itโ€™s the city council, not staff, that is the official purchasing agent, meaning the council would have to formally issue the waiver for Humboldt Made. But thatโ€™s fixable, Black said. If the council decides Humboldt Made is the best fit for the city, Black said thereโ€™s nothing to prevent it from simply voting to approve the waiver before voting to enter into a contract.

But there are potentially more substantial issues with Humboldt Madeโ€™s submittal.

โ€œIn respect to Humboldt Made, they did not have an electronic submittal on Friday the 5th. There was an understanding that the electronic submittal was made but upon investigation that did not turn out to be the case.โ€

โ€œIn respect to Humboldt Made, they did not have an electronic submittal on Friday the 5th,โ€ Black said. โ€œThere was an understanding that the electronic submittal was made but upon investigation that did not turn out to be the case.โ€

Black also indicated city staff was now going through both paper submittals โ€” the one received April 5 and the one received April 8 โ€” side by side to see if any changes were made. Sparks said heโ€™s reviewed that work and there were in fact changes made throughout Humboldt Madeโ€™s entire proposal.

โ€œIt was more extensive than just replacing a duplicate page,โ€ Sparks said. โ€œAs I read through them, it really looked like the Friday copy was a draft that had, I wouldnโ€™t necessarily say typos, but the copy submitted on Monday had been cleaned up. For example, the abbreviation โ€˜HMโ€™ had been changed to โ€˜Humboldt Madeโ€™ and a few paragraphs had undergone a little bit more significant rewrites.โ€

Sparks said none of the prices, numbers or main points of the proposal changed but it appeared the draft submitted Monday had gone through an editing process and โ€œwas just kind of better.โ€

And this mostly aligns with what Powell texted Holmlund on April 7. (Attempts to reach Holmlund to comment on the most recent developments in this story were unsuccessful.)

Reached Friday, Powell said the print copies her staff submitted April 5 were from a rough draft from a couple of weeks earlier. The final draft โ€” which everyone involved had signed off on โ€” was completed by the April 5 deadline, she said, and was a superior draft.

Powell said she never represented to anyone in city staff that the issue was limited to a single page and doesnโ€™t know where that story came from. There was not a duplicate page in the initial proposal submitted to the city.

โ€œ(The duplicate page story) did spark a little curiosity in me that it was so clean because I knew it was a third draft and just to cite that it was a duplicate page, yeah, that did not settle well with me. Did I go to city staff and say, โ€˜Hey guys, I think there were other grammatical errors and other things that were clearly a draft version,โ€™ no I didnโ€™t. Should I have? Sure.โ€

โ€œMy correspondence with the city on submitting our actual final version was very much presented in text message,โ€ she said. โ€œ(The duplicate page story) did spark a little curiosity in me that it was so clean because I knew it was a third draft and just to cite that it was a duplicate page, yeah, that did not settle well with me. Did I go to city staff and say, โ€˜Hey guys, I think there were other grammatical errors and other things that were clearly a draft version,โ€™ no I didnโ€™t. Should I have? Sure.โ€

Informed that the city is now saying it did not receive any digital version of Humboldt Madeโ€™s proposal by the April 5 deadline, Powell indicated that was distressing.

โ€œI was told by my staff that we had submitted it,โ€ she said.

City staff also misrepresented what happened with Vessel Strategiesโ€™ submittal when pointing to it as evidence that Humboldt Made wasnโ€™t the only firm granted a waiver and allowed to submit materials late. While staff repeatedly indicated Vessel Strategies had simply missed the deadline and asked to submit the following Monday, Black said his review indicates Vessel submitted its printed copies of the proposal by deadline Friday but hadnโ€™t uploaded the electronic copy. He said Vesselโ€™s electronic copy was uploaded April 8.

Black said he is drafting a report to present to the city council in closed session Tuesday that will include โ€œthe facts and the legal standard against which they must judgeโ€ them.

โ€œThe legal standard that weโ€™re looking for is did it give one proposer a competitive advantage and, if so, the irregularity would not be considered a minor matter,โ€ he said. “It would put it out of bounds for a waiver.โ€

Asked directly if he felt staff had willfully misrepresented the situation to the public and the council, Sparks said he did not.

โ€œI really donโ€™t believe there was a willful misrepresentation,โ€ he said. โ€œI think it was unfortunately just a comedy of errors. It seems like one error built upon another.โ€

Also reached Friday and informed of the Journalโ€™s findings, Bergel said sheโ€™s disappointed but doesnโ€™t believe she was lied to.

โ€œI find it really hard to believe that our staff would intentionally deceive the public or the council. I find that hard to believe because I believe in our staff. I believe in their integrity.โ€

โ€œI find it really hard to believe that our staff would intentionally deceive the public or the council,โ€ she said. โ€œI find that hard to believe because I believe in our staff. I believe in their integrity.โ€

But Bergel said sheโ€™s confused about how she seemingly got incorrect answers to very direct questions posed at the May 21 meeting, and sheโ€™s saddened that a process that should have been invigorating โ€” asking Eureka to imagine a best version of itself to put forward to the rest of the country and world โ€” has now been tarnished. She said she still feels like the council has two very good proposals before it, no matter how the process proceeds.

โ€œWhat I know, what I believe, is that we will do the right thing, whatever that looks like,โ€ she said. โ€œItโ€™s ugly. Itโ€™s a real bummer. This was something that was supposed to be fun and was really about bringing our community together. My hope is that, in the end, weโ€™ll get there. But I think weโ€™re going to have to walk through some stuff together first.โ€

Related Stories

Thadeus Greenson is the news editor of the North Coast Journal.

Join the Conversation

12 Comments

  1. “We’ll do the right thing whatever that takes”??(Bergel)

    Why start now?

    Our rural city, county, businesses and industries have a long legacy of unreported interrelationships involving family, friends, church and clubs.

    Incompetence invites lawsuits and huge settlements, as if Eureka doesn’t already know.

    For God’s sake, if you’re serious about the “right thing” and not just the “legal standard” return publication of Eureka’s complete staff directory for all city departments so the public can see who’s being hired, promoted and what they do.

    Are you afraid longtime local residents could discover interrelationships between city staff and Humboldt Made? St. Bernard’s?

    Oh, that’s right….staff directories had become common sources of evidence used in court cases alleging nepotism, favoritism, agism, and sexism.

    Can Bergel walk her talk?

  2. The good Old boys are at it again spinning tales, slowing down progression! So they can clinch onto their big pile, Who suffers usually the working class and the community, who are trying to help others and leave a better tomorrow for their kin! #riggedsystem #sorryeureka #sameoldsameold

  3. “asking Eureka to imagine a best version of itself to put forward to the rest of the country and world”

    Haaaaaaa, no seriously. She actually said that with a straight face.

  4. A comedy of errors indeed. The proposal would have spoken for itself, Im sure even the draft. There was no need to try and force it. Its a shame really. The only losers here are the residents.

  5. Humboldt Made is constantly referred to as a “non profit” when it is in fact a privately-owned enterprise organized as a so-called “public benefit” corporation. The appearance of impropriety and the apparent (obvious, really) attempt to game the local scene for fun and nepotistic profit should be justification enough for federal intervention and an IRS audit of this organization and its connections to local political machines.

  6. @Ca4Life – The Good Old Boys may be up for a RICO lawsuit. Bid Rigging is illegal.

  7. I love how Burgle is pretending to be surprised by “seeming to get incorrect answers” regarding the crooked insider deal she herself set up months in advance of getting caught.

  8. Im part of the Humboldt Made creative team. All we hoped to do was apply our considerable skills, energies, and knowledge of Humboldt and Eureka to move the County and the City forward in a genuine and authentic way. We dont need people from across the country to tell us who we are and what to do about it. Working with the community we can do that ourselves, thank you. I fear that poor management of the processes involved will eliminate a worthy group of locals who were ready to give everything weve got for Humboldt and Eureka. Read the proposals folks, and judge for yourselves. And remember, its hard not to be part of an inner circle when the circle is so small to begin with.

  9. Humboldt Made – What about violating the rules of the submission process? Maybe outsiders are what is needed to break the deadly combination of good ole boys network and the outlaw mentality that is so pervasive and sickening.

  10. Sorry Humboldt Made, it might take a few more decades before the memory fades from the costly debacle left behind by the Eureka Chamber of Commerce.

  11. Lane Millar needs to be fired. HumMade needs to be looked at financially by the IRS and state. The city attorney lied during the city council meeting about wrongdoing to council. Eddy-Alexander needs to make Eureka marketing shine in the next 3 years, they won by far IMO and I read it all, sorry. Hope this happens.
    The money going to HM would have quite a bit going to two outside state agencies the first few years and over $28,000 going to 3 of their local consulting board members, not into the two employees with their feet on the ground. Too much convolution IMO.
    The locals here are restless being the only county in CA to lose tax revenue in 2018. It shows more and more everyday, especially in Eureka….they made the bed lied in now. Eureka needs to end all the cronyism and move forward… Friday Night Markets will start soon, the best thing to happen in years though.